After six days of no contact from our prospect companies we decided to take action and follow up our request.
We took the initiative to call Wilcon Builder’s Supply and asked if our request to conduct an ISNA was approved. Luckily the man who answered the phone told that our request was already approved and we were scheduled to conduct the first interview the next Monday, September 14 at 09:00 am.

We also called SM City Davao but the IT officer who received our letter told us that he hasn’t emailed our letter yet to the manager. And he told us again that he will just notify us. One of our classmates told us that SM does not entertain this kind of request (if so it is better if they just told us straight from the moment we submitted the letter…).

We were so glad that finally we will be able to conduct our first real interview and get started with the major paper that we were motivated in making our guide questions for the incoming interview.

…weeeEee^^

0
journal_11

Justify FullSEPTEMBER 1, 2009

We listed our new prospect companies and luckily our instructor approved Wilcon Builder’s Supply and SM City Davao to be our adopted company for the ISNA.

We immediately went to make our request letter signed.



SEPTEMBER 2, 2009

The goal for today is to submit the request letters to our new prospect companies.

First we went to Wilcon Builder’s Supply and personally handed our request letter to one of their managers. She told us that she needs to refer our request to the main office in Manila to be approved and then she will contact us to inform the updates about our request.

Then we proceed to SM City Davao.
We submitted our letter to the IT officer and he notified us that their manager is still in Cebu and he will just contact us if the request is already approved.


…and all along they thought we will
…audition for starstruck…
…bwahahahaha…^^

0
journal_10

AUGUST 31, 2009

Our request to conduct an ISNA at Macondray was denied.

denied…
denied…!?!
denied………!!!!

The request was denied due to necessary renovation in their IT department. They informed us that they cannot accommodate our interview because they the IT department will be very busy during the renovation period.

T_T